Current Programme
| Stage | Programme Date |
|---|---|
| Tenders Issued | December 2004 |
| Tender Return | April 2005 |
| Select Preferred Bidder | November 2005 |
| Contract Award and Financial Close | November 2006 |
| Construction Work (Phase 1) | |
| Strathmore Primary School | In-Service Days: Monday 14 & Tuesday 15 January 2008 To open to pupils 16 January 2008 |
| Whitehills Primary School | In-Service Days: Thursday 31 January & Friday 1 February 2008 To open to pupils 4 February 2008 |
| Burnside Primary School | In-Service Days: 14 & 20 February 2008 To open to pupils 21 February 2008 |
| Woodlands Site | Opened 16 October 2007 |
| Construction Work (Phase 2) | |
| Langlands Primary School Decant to Chapelpark building |
January 2008 to March 2009 In-Service Days: 4 and 5 February 2008 Pupils start: 6 February 2008 |
| Carlogie Primary School Decant to Kinloch building |
February 2008 to October 2008 In-Service Days: 20 and 21 February 2008 Pupils start: 22 February 2008 |
| Construction Work Carnoustie High School - new Teaching block |
November 2006 to December 2008 |
| Carnoustie High School - Demolitions and external works |
January 2009 to July 2009 |