Current Programme

Stage Programme Date
Tenders Issued December 2004
Tender Return April 2005
Select Preferred Bidder November 2005
Contract Award and Financial Close November 2006
Construction Work (Phase 1)
Strathmore Primary School In-Service Days: Monday 14 & Tuesday 15 January 2008
To open to pupils 16 January 2008
Whitehills Primary School In-Service Days: Thursday 31 January & Friday 1 February 2008
To open to pupils 4 February 2008
Burnside Primary School In-Service Days: 14 & 20 February 2008
To open to pupils 21 February 2008
Woodlands Site Opened 16 October 2007
Construction Work (Phase 2)
Langlands Primary School
Decant to Chapelpark building
January 2008 to March 2009
In-Service Days: 4 and 5 February 2008
Pupils start: 6 February 2008
Carlogie Primary School
Decant to Kinloch building
February 2008 to October 2008
In-Service Days: 20 and 21 February 2008
Pupils start: 22 February 2008
Construction Work
Carnoustie High School - new Teaching block

November 2006 to December 2008
Carnoustie High School -
Demolitions and external works
January 2009 to July 2009