Development Plan Scheme and Participation Statement

Contents


Appendix A – Detailed Timetable of LDP Process

Evidence Report

Substage: Preparation of Evidence Report (including early engagement)

Impact Assessment: Preparation of SEA Scoping Report, EQIA, Fairer Scotland Duty Assessment, and the Public Sector Equality Duty. Submit Scoping Report to Consultation Authorities (5 weeks)

Indicative timeframe (financial year quarters): Q1 2023 – Q1 2024


Substage: Draft Evidence Report to Council for approval for consultation

Indicative timeframe (financial year quarters): Q2 2024


Substage: Consultation (6 Weeks)

Indicative timeframe (financial year quarters): Q2 2024


Substage: Addressing comments and disputes on Evidence Report

Indicative timeframe (financial year quarters): Q3 2024


Substage: Finalising Evidence Report

Indicative timeframe (financial year quarters): Q3 2024 – Q4 2024/25


Substage: Evidence Report at Council for approval

Indicative timeframe (financial year quarters): Q4 2024/25


Substage: Publication of Evidence Report

Indicative timeframe (financial year quarters): Q4 2024/25 – Q2 2025


Gatecheck

Substage: Evidence Report at Gatecheck

Indicative timeframe (financial year quarters): Q4 2024/25 – Q2 2025


Substage: Sufficiency Report from DPEA on Gatecheck and authorisation to proceed to proposed plan

Indicative timeframe (financial year quarters): Q2 2025


Proposed plan and examination

Substage: Preparation of proposed plan and engagement

Impact Assessment: Preparation of SEA Environmental Report and HRA

Indicative timeframe (financial year quarters): Q2 2025-Q3 2027


Substage: Proposed Plan and associated assessments at Council for approval to consult

Indicative timeframe (financial year quarters): Q 4 2027/28


Substage: Consultation proposed plan (12 weeks)

Impact Assessment: Consult on SEA Environmental Report. Publication of other assessments and strategies (including submission of HRA to Nature Scot)

Indicative timeframe (financial year quarters): Q4 2027/28 – Q1 2028


Substage: Preparation of Schedule 3 forms

Indicative timeframe (financial year quarters): Q1 2028 – Q2 2028

The preparation and submission of Schedule 3 forms is another statutory requirement for local authorities during the LDP process. They are linked to the issues brought forward during the consultation period, specifically focussing on any unresolved issues. These forms were previously known as Schedule 4s and will contain information and summaries of all unresolved issues and representations at that point in time, alongside reasonings as to why Angus Council did not modify the plan based on these representations.


Substage: Schedule 3 forms at Council for approval to submit for Examination

Indicative timeframe (financial year quarters): Q2 2028


Substage: Submission for Examination

Indicative timeframe (financial year quarters): Q3 2028


Substage: Examination Period

Indicative timeframe (financial year quarters): Q3 2028 – Q2 2029 (assuming timescales aforementioned)


Substage: Consideration of examination report and modifications to Proposed Plan

Impact Assessment: Revise SEA Environmental Report to reflect appropriate modifications from examination

Indicative timeframe (financial year quarters): Q2 2029 – Q3 2029


Substage: Intent to adopt LDP process and submission to Scottish Government

Impact Assessment: Submit amended environmental report and agreed HRA to Scottish ministers

Indicative timeframe (financial year quarters): Q3 2029


Substage: LDP Adoption

Impact Assessment: Prepare and publish SEA Post-adoption statement

Indicative timeframe (financial year quarters): Q3 2029


Delivery programme

Substage: Preparation of Delivery Programme

Indicative timeframe (financial year quarters): Q3 2029 – Q4 2029/30


Substage: Delivery Programme at Council for approval

Indicative timeframe (financial year quarters): Q4 2029/30


Substage: Publication of Delivery Programme

Indicative timeframe (financial year quarters): Q4 2029/30